Título
[en] DATA-DRIVEN JOINT CHANCE-CONSTRAINED OPTIMIZATION FOR THE WORKOVER RIG SCHEDULING PROBLEM
Título
[pt] OTIMIZAÇÃO COM RESTRIÇÕES CONJUNTAS PROBABILÍSTICAS ORIENTADA POR DADOS PARA O PROBLEMA DE PROGRAMAÇÃO DE SONDAS DE INTERVENÇÃO
Autor
[pt] IURI MARTINS SANTOS
Vocabulário
[pt] MODELOS DE REGRESSAO
Vocabulário
[pt] RESTRICOES PROBABILISTICAS CONJUNTAS
Vocabulário
[pt] OTIMIZACAO ORIENTADA SOBRE DADOS
Vocabulário
[pt] OTIMIZACAO SOB INCERTEZA
Vocabulário
[pt] PROGRAMACAO DE SONDAS
Vocabulário
[en] REGRESSION MODELS
Vocabulário
[en] JOINT CHANCE CONSTRAINTS
Vocabulário
[en] DATA-DRIVEN OPTIMIZATION
Vocabulário
[en] OPTIMIZATION UNDER UNCERTAINTY
Vocabulário
[en] RIG SCHEDULING PROBLEM
Resumo
[pt] As sondas de intervenção são um recurso crucial na exploração e
produção de petróleo, sendo utilizadas nas operações de manutenção de
poços. As empresas de petróleo planejam quais sondas atenderão os poços. O
Problema de Programação de Plataforma de Trabalho (WRSP) determina
quais sondas atenderão os poços e quando as atividades ocorrerão. Com
o intuito de auxiliar o WRSP, esta tese propõe uma metodologia de
otimização orientada por dados (DD) baseada em regressão, aplicandoa em instâncias reais. Essa abordagem de otimização DD é dividida em
três fases: tratamento de dados, onde técnicas de mineração de texto e
agrupamento são usadas para refinar e recuperar informações dos dados;
modelagem preditiva usando regressão de cume para estimar a duração
do workover e as incertezas endógenas do modelo; otimização, onde a
previsão da regressão e seu erro aleatório são inseridos nos modelos de
restrições probabilísticas conjuntas (JCC), gerando soluções mais resilientes
às incertezas. Propomos uma formulação estocástica de JCC baseada em
simulação e distância de Wasserstein para gerar cenários e reduzir o tamanho
do problema. Esse modelo é comparado com quatro alternativas: um DD
não estocástico, um CC integrado estocástico, um modelo estocástico com
restrição orçamentária e a abordagem atual da empresa. Para instâncias
de pequeno e médio porte, o modelo estocástico JCC garante um nível de
confiança de viabilidade e um erro de aproximação inferior a 5 por cento. No entanto,
o modelo estocástico JCC não fecha o GAP em instâncias maiores. Para
essas instâncias, o modelo DD não estocástico é uma boa alternativa com
perturbações não superiores a 10 por cento. No geral, a metodologia de otimização
DD encontra cronogramas que são mais frequentemente viáveis e com custos
menores em comparação com o método da empresa.
Resumo
[en] Workover rigs are a crucial resource in petroleum exploration and
production, used in the wells maintenance operations. The Workover Rig
Scheduling Problem (WRSP) determines which rigs will serve the wells and
when the activities will occur. This decision-making problem emerges in a
highly uncertain environment, and most literature approaches are based on
deterministic models and heuristics. Aiming to assist the WRSP, this thesis
proposes a regression-based data-driven (DD) optimization methodology,
applying it in real-life-based instances. This DD optimization approach
is composed of three phases: data treatment, where text mining and
clustering techniques are used to refine and retrieve information from the
data; predictive modeling, using ridge regression to estimate the workover
duration and the endogenous uncertainties in the model; optimization,
where the regression prediction and random error are inserted in the joint
chance-constrained (JCC) models, generating solutions more resilient to the
uncertainties. We propose a stochastic JCC formulation based on simulation
and Wasserstein distance to generate scenarios and reduce the problem
size. This model is compared with four alternatives: a non-stochastic DD,
a stochastic integrated CC, a stochastic budget-constrained model, and the
company s current approach. For small and medium-sized instances, the
stochastic JCC model guarantees a feasibility confidence level with an error
of approximating lower than 5 percent. However, the stochastic JCC model does
not close the GAP in large instances. For these instances, the non-stochastic
DD model is a good alternative with disturbances not greater than 10 percent.
Overall, the DD optimization methodology finds schedules that are more
often feasible and with lower costs compared with the company s method.
Orientador(es)
SILVIO HAMACHER
Coorientador(es)
FABRICIO CARLOS PINHEIRO OLIVEIRA
Banca
SILVIO HAMACHER
Banca
FABRICIO CARLOS PINHEIRO OLIVEIRA
Banca
VIRGILIO JOSE MARTINS FERREIRA FILHO
Banca
PAULO CESAR RIBAS
Banca
GLAYDSTON MATTOS RIBEIRO
Banca
LEONARDO DOS SANTOS LOURENCO BASTOS
Catalogação
2023-02-23
Apresentação
2022-12-13
Tipo
[pt] TEXTO
Formato
application/pdf
Idioma(s)
INGLÊS
Referência [pt]
https://www.maxwell.vrac.puc-rio.br/colecao.php?strSecao=resultado&nrSeq=61875@1
Referência [en]
https://www.maxwell.vrac.puc-rio.br/colecao.php?strSecao=resultado&nrSeq=61875@2
Referência DOI
https://doi.org/10.17771/PUCRio.acad.61875
Arquivos do conteúdo
NA ÍNTEGRA PDF